By Abdul Ghani
The Federal Government Employees Housing Authority (FGEHA) is evaluating a public-private partnership (PPP) and asset-swap mechanism to complete the remaining work on 1,869 apartments over an estimated period of three years.
According to an official document available with Wealth Pakistan, the proposed mechanism would use the project's commercial inventory to complete the remaining residential work while minimising the financial burden on members who have already invested in the housing scheme.
The project has been largely stalled since the termination of the joint venture agreement in 2021. The FGEHA has since navigated contractual, legal, audit and winding-up procedures to address outstanding issues and determine the remaining development cost.
The total receivables from members stand at approximately Rs13.37 billion, against which Rs10.30 billion has been collected.
As part of the process, an independent audit firm was hired to conduct the audit and winding-up of EHFPRO, while the FGEHA's Technical Wing evaluated the cost of the remaining work.
The grey structure of the project's 10.10-acre component is substantially complete, except for one 10-storey residential tower and one five-storey commercial tower. Finishing work and external utility services, however, remain outstanding.
The Authority is considering the proposed PPP and asset-swap arrangement and mobilizing resources for the remaining construction without passing the entire additional cost on to existing allottees. The approach is intended to balance the completion requirements with the financial interests of apartment owners.
Completing the 1,869 apartments will require approximately three years after construction begins. However, the proposal does not specify a confirmed start date or a final deadline for the outstanding work.
The authority has also stressed the need for a clear, time-bound completion plan supported by regular monitoring to ensure progress on the remaining residential and allied infrastructure.

Credit: INP-WealthPk